Construction underway on new Sydney Light Rail stop

News Date: 17 Jul 2017

Category: Railways

NSW Premier Gladys Berejiklian has given an update on the progress of the Sydney Light Rail project, revealing that more than a third of the track installed and that construction is now underway on the first of 19 light rail stops from the City to the south east.

“At the start of the year we had 500 metres of track in the ground. As of today we have more than 8000 metres, which is more than a third of the track now in place,” Ms Berejiklian said.

“It is great to see that we have finished installing more than one kilometre of track on Alison Road at Randwick and that work is now underway at the Wansey Road light rail stop which will be the first one completed in the next couple of months.”

Track installation in the Randwick area is an important first step towards the testing and commissioning of the light rail system.

“We are also seeing progress in the CBD, with cars returning to part of George Street near Circular Quay where track has been installed including paving laid between the rails,” Ms Berejiklian said.

Each light rail vehicle will be able to carry up to 450 people, equivalent to up to nine standard buses. With up to 15 light rail vehicles an hour operating in each direction on opening, this gives a capacity of 13,500 passengers per hour. This will mean less congestion on Sydney’s roads and more reliable travel times.

The Premier said: “This demonstrates the NSW Government’s commitment to delivering important transport infrastructure on time and on budget.”

Sydney Light Rail will provide high frequency ‘turn up and go’ transport services from Circular Quay to Randwick and Kingsford from 2019.

More Industry & Project News

Tenders open for Midland Highway upgrades

Tenders are now open to deliver the next two major projects under the Midland Highway 10 Year Action Plan, with the upgrades set to improve road safety and save lives.


Toodyay Road safety upgrades to begin shortly

The Western Australian State Government has announced that work on a series of new safety upgrades to Toodyay Road is expected to begin before the end of the year.


Design works underway on $4.5 million Kingaroy School hall

Queensland Premier Annastacia Palaszczuk has revealed that works to design the new 4.5 million Kingaroy State High School hall is underway, with construction on the hall set to start in November.


$65m Centenary Highway upgrade announced

The Queensland State Government will spend $65 million to transform one of the busiest intersections on one of South East Queensland’s busiest roads – the Sumners Road Interchange on the Centenary Highway.


Construction begins on new Tamworth Sporting Centre

Construction has begun on the $17.2 million Northern Inland Centre of Sporting Excellence in Tamworth.